Rule 63003 - Actual Date is not in the future

Rule Type Rejection

Validated Data

This rule is used to validate:

  • Actual Date of Control Schedule- to confirm that the control schedule is not updated on or after the actual date.

To perform this validation, the following information is used:

Description

Control schedule cannot be updated because the current Actual Date is not in the future. You can only update the control schedule when the actual date is in the future.

Additional Notes

N/A

Message

When this validation rule is triggered, the following message is returned:

Control Schedule Not In Future. The control schedule can only be updated or deleted when the actual date is in the future.

Applies To

This rule applies to:

Change History

  • Release 6.05 - Created

Upcoming Changes

The following changes are expected to be implemented in an upcoming release (or include the release # if known).